Monday, July 6, 2015

Phoenix Motorists traveling I-10 to CA should expect delays east of Quartzsite

Phoenix motorists traveling to California should plan ahead, expect possible delays

ADOT to start Interstate 10 pavement work east of Quartzsite today
PHOENIX – Motorists traveling to and from California along Interstate 10 need to plan ahead and allow extra travel time as the Arizona Department of Transportation starts a pavement improvement project in La Paz County east of Quartzsite, beginning on Monday, July 6.
Approximately 90 miles west of downtown Phoenix, crews will remove and replace pavement on the westbound and eastbound lanes along an 11-mile segment of I-10 (mileposts 41-52).
The work is scheduled to take place weekdays during daylight hours between 6 a.m. and 4 p.m. During work hours, I-10 will be narrowed to one lane in both directions.
The speed limit will be reduced to 55 mph through the work zone. Drivers are advised to plan for delays of up to 15 minutes.
No work is scheduled on weekends or holidays. The $8.1 million improvement project is scheduled to be completed by this fall.
ADOT works to inform the public about planned highway restrictions, but there is a possibility that unscheduled closures or restrictions may occur. Weather can also affect a project schedule. To stay up to date with the latest highway conditions around the state, visit the ADOT Traveler Information Center at az511.govor call 511.

Thursday, July 24, 2014

Intermittent I-10 closures between Quartzsite & Tonopah Sunday

APS to close I-10 between Tonopah and Quartzsite this Sunday

Overhead power lines 
will installed over the interstate 

PHOENIX – Drivers traveling between Phoenix and California on Interstate 10 on Sunday morning, July 27, need to plan ahead and allow extra travel time as the highway will be closed intermittently between mileposts 67-68 as APS installs power lines over the interstate, according to the Arizona Department of Transportation.
Arizona Department of Public Safety officers will stop traffic several times from 5 to 9 a.m. Sunday up to 15 minutes each time to allow APS crews to make the aerial crossings. The location of the work is about 75 miles east of Quartzsite and 43 miles west of the SR 85 junction in Buckeye.
Drivers can expect delays and congestion approaching the I-10 closure. The speed limit will be reduced near the work zone and flaggers will be present.
ADOT works to inform the public about planned highway restrictions, but there is a possibility that unscheduled closures or restrictions may occur. Weather can also affect a project schedule. To stay up-to-date with the latest highway conditions around the state, visit the ADOT Traveler Information Center atwww.az511.gov or call 5-1-1.

Wednesday, April 9, 2014

Temporary 12-hour ramp closures I-10 Exit 1 in Ehrenberg


Temporary 12-hour ramp closures at I-10 Ehrenberg (Exit 1)   
Motorists are advised to use adjacent ramps

As part of the ongoing improvements in Ehrenberg, the Arizona Department of Transportation will temporarily close the on-and-off ramps for approximately 12 hours between the midnight and noon Thursday, April 10 and Friday, April 11 at Interstate 10 Ehrenberg (Exit 1).

Ramps will be closed intermittently for milling and repaving each day. Motorists are advised to either exit in Quartzsite or Blythe to access Juneau Avenue/Poston Road.

For more information, please contact the Project Hotline at 1.855.712.8530, or email at Projects@azdot.gov. To stay up-to-date with the latest highway conditions around the state, visit the ADOT Traveler Information Center at www.az511.gov or call 511.

Thursday, March 27, 2014

I-10 delays tonight and Friday between Ehrenberg & Quartzsite


Westbound I-10 to close briefly overnight for rock removal 
near Arizona-California state line
Motorists traveling between Quartzsite and Ehrenberg 
should allow extra travel time

The Arizona Department of Transportation is advising motorists traveling on Interstate 10 near the California-Arizona state line to allow extra travel time due to the start of a three-week project to remove large rocks alongside the highway between Ehrenberg and Quartzsite this week.

Drivers traveling late at night on westbound I-10 (mileposts 10-11) on Thursday, March 27 and Friday, March 28 need to be prepared for intermittent closures up to 20 minutes for blasting and rock removal. Work will take place between 8 p.m. and 6 a.m.

Additionally, I-10 will be narrowed to one lane in each direction through the work zone until the project is completed in mid-April.

Message boards will be in place to inform motorists of lane restrictions and speed reductions. Law enforcement will be in place to monitor traffic and enforce the speed limit. Motorists are advised to allow extra travel time through the area.

For more information, please contact the Project Hotline at 1.855.712.8530, or email atProjects@azdot.gov.To stay up to date with the latest highway conditions around the state, visit the ADOT Traveler Information Center at az511.gov or call 5-1-1.

Monday, May 13, 2013

Pavement maintenance scheduled this week east of Quartzsite


Arizona Department of Transportation

Pavement maintenance scheduled next week on I-10 east of Quartzsite
Pavement maintenance scheduled this week on I-10 east of Quartzsite
Motorists advised to plan ahead and allow extra travel time

Arizona Department of Transportation maintenance crews will begin asphalt repairs along a 22-mile segment of Interstate 10 east of Quartzsite beginning Monday, May 13 through May 24.

What to expect:
  • Work will take place weekdays between 5 a.m. - 7 p.m.
  • One lane will be restricted in each direction from mileposts 30-52.
  • Motorists are advised to plan ahead and allow extra travel time.
  • Message boards will be displayed to inform drivers of lane restrictions.
  • Law enforcement will be on-site to control traffic and monitor speeds.
ADOT works to inform the public about planned highway restrictions, but there is a possibility that unscheduled closures or restrictions may occur. Weather can also affect a project schedule.

For more information, please visit www.azdot.gov/statewide or contact the Project Hotline at 1-855-712-8530, or email at Projects@azdot.gov. To stay up-to-date with the latest highway conditions around the state, visit the ADOT Traveler Information Center at www.az511.gov or call 5-1-1.


Monday, June 4, 2012

Night construction on I-10 east of Quartzsite


Arizona Department of Transportation

ADOT on Facebook  ADOT on Twitter  ADOT on YouTube  

Pavement maintenance this week on Interstate 10 east of Quartzsite

The Arizona Department of Transportation will be repaving eastbound and westbound I-10, east of Quartzsite on mileposts 30 – 52, beginning Tuesday (June 5) through Thursday (June 14). 

The nightly work is scheduled as follows:

Tuesday (June 5) to Thursday (June 7)
Eastbound and westbound I-10 will have intermittent lane closures from 7 p.m. to 10 a.m. the following morning. 

Sunday (June 10) to Thursday (June 14)
Eastbound and westbound I-10 will have intermittent lane closures from 7 p.m. to 10 a.m. the following morning. 

One lane will be open at all times. Crews and law enforcement will be on site to direct traffic and message boards and signs will guide drivers through the area.
The schedule is subject to change due to a variety of reasons, including weather, availability of materials, and mechanical difficulties. ADOT advises drivers to proceed through or near work zones with caution, slow down, and be alert for construction equipment and personnel.
For more information about this project, please visit www.azdot.gov/statewide or contact Yuma District Senior Community Relations Officer Gabriella Kemp at 928.317.2165, gkemp@azdot.gov or ADOT Community Relations Officer, Paki Rico, at 520-388-4233, prico@azdot.gov.


Thursday, August 18, 2011

Intermittent lane closures on Interstate 10 east of Quartzsite begin Monday



Motorists should expect 15 minute delays


The Arizona Department of Transportation will begin to repair segments of pavement along Interstate 10 between Quartzsite and the Bouse Wash Rest Area Monday (Aug. 22) and through Wednesday (Aug. 31). Intermittent lane closures are planned during work hours which will take place between 2 a.m. and 6 p.m. each day. There will be no work on Fridays or over the weekend. Drivers should plan ahead and expect approximately 15 minute delays.

The work consists of removing and replacing pavement along segments of eastbound and westbound I-10 beginning east of Quartzsite to the Bouse Wash Rest Area. Trucks carrying loads wider than 12 feet will not be allowed to travel through the work zone during work hours.

Message boards will advise drivers of lane restrictions. To ensure safety in the work zone, the speed limit will be reduced to 45 mph. Law enforcement will be on-site to help monitor speeds and control traffic.

ADOT advises drivers to proceed through the work zone with caution, slow down and be alert for construction equipment and personnel.

ADOT works to inform the public about planned highway restrictions, but there is a possibility that unscheduled closures or restrictions may occur. Weather can also affect a project schedule. To stay up-to-date with the latest highway conditions around the state, visit the ADOT Traveler Information Center at www.az511.gov or call 5-1-1.

Monday, May 23, 2011

Memorial Day alert: allow extra time for work zone 40 miles w. of Phoenix

I-10 Memorial Day weekend alert: Allow extra travel time for bridge work zone
40 miles west of Phoenix


PHOENIX – If you’re using Interstate 10 between Phoenix and California over the Memorial Day weekend, be sure to plan ahead and allow extra travel time, especially before and at the end of the weekend, according to the Arizona Department of Transportation.

While no construction work is scheduled over the weekend, heavy holiday traffic is expected to back up along I-10 at the Hassayampa River bridges work zone 40 miles west of downtown Phoenix. I-10 is narrowed to one lane in each direction in the area (milepost 105), with traffic sharing one bridge while the second bridge is undergoing upgrades.

ADOT has the following recommendations for drivers planning to use I-10 between Phoenix and California just before and during the holiday weekend:

•Travel through the area during non-peak hours, including early morning or late night. Traffic is expected to be heaviest during the afternoon and early evening hours on Thursday and Friday (May 26-27) and again on Monday (May 30).
•Allow extra travel time. Delays of approximately 90 minutes may occur during the busiest hours before and at the end of the weekend.
•Consider alternate routes, including US 60 through Wickenburg or Interstate 8 (via State Route 85 in the Phoenix area and US 95 north of Yuma).

ADOT will provide updates about heavier I-10 traffic conditions on its Travel Information site at www.az511.gov or by calling 5-1-1 from within the state.

The $3.9 million I-10 Hassayampa Bridges Improvement Project started in fall 2010. It is scheduled for completion this summer.

For the latest news on major existing highway work zones, visit the ADOT website at www.azdot.gov. Information about Memorial Day travel plus ADOT projects and programs is available via the ADOT Blog at http://adotblog.blogspot.com.

Monday, April 25, 2011

I-10 Lane closures near Quartzsite-

Tom Wells Road (Exit 5) at Interstate 10 near
California state line temporarily closed Tuesday


Several ramps and lanes to close over next few weeks as workers seal pavement cracks

YUMA - The Arizona Department of Transportation is currently working to extend the life of the pavement on a 32-mile stretch of Interstate 10 near the California state line. As part of this highway maintenance project, workers will need to implement periodic closures of Tom Wells Road (Exit 5) from 6 a.m. to 6 p.m. Tuesday (April 26) to access and repair cracks in the pavement.

Other ramps, lanes and overpasses throughout the project area will also be affected as the project progresses along this stretch of I-10. Ramp closures will be in effect for several hours each day and will be reopened as soon as possible. At some exits, the roadway on the overpasses will be repaired and crews will direct traffic through the area.

Additional closures are scheduled from 6 a.m. to 6 p.m. each day as follows:
•Monday (May 2) and Tuesday (May 3) - Access to Ehrenberg via Posten Road (Exit 1)
will be temporarily restricted while crews work on I-10 lanes.

•Thursday (May 5) and Friday (May 6)- Riggles Avenue (Exit 19) in Quartzsite will be
temporarily closed while crews work on I-10 lanes.

•Monday (May 9) and Tuesday (May 10) - US 60 (Exit 31) will be temporarily closed
while crews work on I-10 lanes.

Message boards will direct motorists to detours using the nearest open ramp. Law enforcement will be on site to direct traffic and monitor speeds.

This project is scheduled for completion in May 2011.

ADOT advises drivers to proceed through the work zone with caution, slow down and be alert for construction equipment and personnel.

ADOT works to inform the public about planned highway restrictions, but there is a possibility that unscheduled closures or restrictions may occur. Weather can also affect a project schedule. To stay up-to-date with the latest highway conditions around the state, visit the ADOT Traveler Information Center at www.az511.gov or call 5-1-1.

For more information about this project, please visit www.azdot.gov/statewide or contact Yuma District Senior Community Relations Officer Gabriella Kemp at 928.317.2165 or gkemp@azdot.gov. Local media should contact the ADOT Public Information Office at news@azdot.gov or 1.800.949.8057. Visit www.facebook.com/azdot or www.azdot.gov for more information about ADOT.





Thursday, April 21, 2011

I-10 paving delays near Quartzsite

Pavement maintenance on Interstate 10
near Quartzsite begins Monday


Lane Closures for six miles near California border

YUMA - The Arizona Department of Transportation will begin work Monday (April 25) to seal cracks in the pavement on a 32-mile stretch of Interstate 10 starting at the California border. Initially, a six-mile segment of the highway will be temporarily restricted to one lane in each direction as crews work on the road surface.

Work is scheduled to take place from 6 a.m. to 6 p.m. Monday through Friday. The project is scheduled for completion in May.

There will be message boards and signs to warn drivers of the construction zone and reduced speed limit of 55 miles per hour. Law enforcement will be on site to control traffic and monitor speed.

ADOT advises drivers to proceed through the work zone with caution, slow down and be alert for construction equipment and personnel.

ADOT works to inform the public about planned highway restrictions, but there is a possibility that unscheduled closures or restrictions may occur. Weather can also affect a project schedule. To stay up-to-date with the latest highway conditions around the state, visit the ADOT Traveler Information Center at www.az511.gov or call 5-1-1.

For more information about this project, please visit www.azdot.gov/statewide or contact Yuma District Senior Community Relations Officer Gabriella Kemp at 928.699.8983 or gkemp@azdot.gov. Local media should contact the ADOT Public Information Office at news@azdot.gov or 1.800.949.8057. Visit www.facebook.com/azdot, www.twitter.com/ArizonaDOT or www.azdot.gov for more information about ADOT.

Saturday, November 27, 2010

Drivers encouraged to allow extra travel time for trips home at end of holiday weekend

PHOENIX — Travelers heading home on state highways to wrap up the holiday weekend are encouraged to allow extra travel time and get an earlier start due to anticipated heavy traffic Sunday afternoon and evening (November 28). The Arizona Department of Transportation says traffic backups can be expected approaching some existing work zones, although construction work will not resume until next week. Among the safety improvement locations where delays should be anticipated:

Interstate 10 approximately 11 miles west of the State Route 85 junction west of the Phoenix area: A major bridge repair project at the Hassayampa River has required the closure of the westbound I-10 bridge. I-10 is limited to one lane in each direction on the eastbound bridge. Drivers are encouraged to allow at least 90 minutes of extra travel time in the area Sunday afternoon and evening due to busy traffic conditions. Travelers also can consider alternate routes, including US 60 through Wickenburg and Salome to travel beyond the bridge repair site. The US 60 junction with I-10 is east of Quartzsite in western Arizona.

State Route 87 between the Phoenix area and Payson: A highway widening and shoulder improvement project five miles north of the Bush Highway/Saguaro Lake turnoff (south of Sunflower) limits travel to one lane in each direction. Heavier traffic, especially in the southbound direction, should be expected.

Grand Avenue (US 60) in the Phoenix region: New lanes were opened Wednesday (November 24) between 83rd Avenue and Loop 101. However, an existing work zone with limited lanes remains in place between Loop 101 and Loop 303.

Interstate 17 between Flagstaff and Phoenix: Although no major lane restrictions are in place this weekend, drivers are encouraged to allow extra travel time Sunday due to anticipated heavier traffic.

ADOT reminds drivers to remember the following safe driving tips: Be patient, do not follow other vehicles too closely; obey speed limits; buckle up and never drive while impaired. Information about highway conditions is available on ADOT's Travel Information site at www.az511.gov or by calling 5-1-1.

Tuesday, November 23, 2010

Update: Paving project on I-10 near Harquahala Valley Road to start on Monday

Drivers can expect ten miles of one-lane traffic

YUMA - Paving is scheduled to begin Monday, Nov. 29 along 10 miles of Interstate 10 between the Maricopa county line and Harquahala Valley Road near Salome.

Beginning Nov. 29, commuters can expect the following:

•One westbound and one eastbound lane will be closed between 7 a.m. and 5 p.m. Monday through Thursday to allow crews to access the roadway safely.

•The speed limit through the work zone will be reduced to 45 mph.

•Drivers can expect delays of up to 15 minutes.

•Loads wider than 14 feet will be allowed to travel through the area on Fridays, Saturdays and Sundays, when paving operations are not taking place.

Message boards will be displayed to inform commuters of construction. Law enforcement officers will be present along the work zone to control traffic and monitor speeds.

Paving is expected to be completed by December 16.

ADOT will fill cracks and apply material to protect the roadway on I-10 near Harquahala Valley Road. Over time, varying temperatures, along with traffic, have worn down the roadway surface, creating small cracks. This project will seal the highway surface, preventing water from seeping into the cracks and damaging the base layer of pavement. Performing preventative maintenance is a cost-effective method for extending the life of the roadway.
As always, drivers are reminded to proceed through the work zone with caution, slow down, and be alert for construction equipment and personnel.
ADOT works to inform the public about planned highway restrictions, but there is a possibility that unscheduled closures or restrictions may occur. Weather can also affect a project schedule. To stay up-to-date with the latest highway conditions around the state, visit the ADOT Traveler Information Center at www.az511.gov or call 5-1-1.

For more information regarding this project, please contact Gaby Gonzalez at (928) 699-8983 or e-mail ggonzalez@azdot.gov.